Commissioning is where an assembled plant becomes a producing plant. Our engineers run it with your crew, so training happens on the plant you will operate. Below is a typical day-by-day sequence for a mid-size batch plant — actual days depend on plant size, crew experience and whether materials are ready.

Before commissioning: what must be ready

Item Why
Mechanical installation complete All units placed, bolted, ducts and lines connected
Power Grid or generator at the right voltage and frequency
Fuel Enough for trials and the first production days
Bitumen In the tank at pumping temperature
Aggregate Every size in its bay and bin
Test weights For scale calibration
Trucks To take trial mixes away
Lab and technician To test trial mixes
Crew Operators, maintenance mechanic and electrician present every day

A typical commissioning sequence

Day Work Training focus
1 Pre-start checks: mechanical, electrical, lubrication, safety devices; motor rotation Plant layout, safety rules, lock-out/tag-out
2 No-load runs of every unit; interlocks; emergency stops; control system I/O checks Control screens, start-up and shutdown sequence
3 Scale calibration (aggregate, filler, bitumen); cold feeder calibration Calibration method and records
4 Burner set-up: ignition, flame, air-fuel ratio; drum heating with aggregate Burner control, temperature management
5 Trial batches: temperatures, mixing times, discharge; adjust recipes Recipe entry, batch monitoring, alarms
6 Trial production with your lab: gradation, binder content, temperatures Quality checks, adjustments
7 Production under supervision; punch list; handover Daily checks, lubrication, wear parts, plant log

Containerized and mobile plants often move faster through days 1–2 because units arrive pre-wired and tested.

Training by role

Role What they learn
Plant operator Start-up and shutdown; recipes; burner and temperature control; alarms; batch records
Maintenance mechanic Daily to monthly checks; lubrication; belt, chain, liner and paddle replacement; baghouse care
Electrician Cabinets, motors, sensors, interlocks; fault finding with the control system
Plant manager Production planning; fuel and output records; spare parts stock; safety

Handover documents

  • Operating and maintenance manuals
  • Electrical drawings and parts lists
  • Calibration records for scales and feeders
  • Burner settings record
  • Lubrication chart and maintenance schedule
  • Punch list, signed when closed

Common delays — and how to avoid them

Delay Prevention
No fuel or bitumen at temperature Deliver and heat before engineers arrive
Missing aggregate sizes Fill every bay and bin
No trucks for trials Book them for trial days
Crew changes every day Same trainees throughout
Power problems Test the generator or grid supply with load beforehand

Our service page explains how engineers’ days are agreed in the contract. For the steps before commissioning, see installation time. Plan commissioning with us.