A batch plant’s output is simply batch size × batches per hour. A twin-shaft mixer that takes 1,500 kg and completes a cycle every 45 seconds — 80 cycles an hour — produces 120 t/h. Change either number and the output changes.
What happens in one cycle
| Phase | What happens | Typical share of the cycle |
|---|---|---|
| Weighing | Aggregate, filler and bitumen are weighed in their hoppers — overlapping with the previous mix | Overlaps |
| Aggregate and filler discharge | Hot aggregate and filler drop into the mixer | A few seconds |
| Dry mixing | Aggregate and filler blend before the binder | Several seconds |
| Bitumen injection | Bitumen is sprayed into the mixer | A few seconds |
| Wet mixing | Binder coats every particle | The longest phase |
| Discharge | Mixer gates open into the truck or silo skip | A few seconds |
Because the next batch is weighed while the current one mixes, the cycle is set mainly by discharge + dry mix + wet mix + discharge.
Output by mixer size and cycle time
| Mixer (kg/batch) | 45 s cycle (80/h) | 50 s cycle (72/h) | 60 s cycle (60/h) |
|---|---|---|---|
| 750 | 60 t/h | 54 t/h | 45 t/h |
| 1,000 | 80 t/h | 72 t/h | 60 t/h |
| 1,500 | 120 t/h | 108 t/h | 90 t/h |
| 2,000 | 160 t/h | 144 t/h | 120 t/h |
| 3,000 | 240 t/h | 216 t/h | 180 t/h |
| 4,000 | 320 t/h | 288 t/h | 240 t/h |
These match the mixer sizes in our stationary batch plant series: the RMX-B120 has a 1,500 kg mixer, the RMX-B160 a 2,000 kg mixer, and so on.
Mixes that need longer cycles
| Mix | Why it takes longer |
|---|---|
| Stone mastic asphalt (SMA) with fibers | Fibers must be dispersed evenly |
| Polymer-modified binders | Higher viscosity; coating takes longer |
| High RAP content | RAP must blend and transfer heat with new aggregate |
| Fine or high-binder mixes | More surface area to coat |
When you plan a contract with these mixes, calculate output with the longer cycle — or choose a larger mixer.
The mixer is only one link
The mixer can only mix what the plant supplies:
- Drying drum and burner must dry and heat enough aggregate per hour at your moisture — see rated vs real output
- Hot elevator and screen must carry and split that flow
- Hot bins must hold enough of each size between batches
- Trucks or silo must take each batch as it is discharged
A balanced plant has every link sized for the same output — compare all of them when you compare quotes.
Questions to ask your supplier
- What mixer size and standard cycle time give the rated output?
- What is the minimum cycle time with my mix and specification?
- Can the drum supply the rated output at my wet-season moisture?
- Is there room for a fiber feeder or additive dosing if I need SMA or modified mixes?