An 80 t/h plant makes about 400–550 tons of mix in an 8-hour shift — enough for one busy paving crew or two smaller ones. That covers most provincial and district road contracts, municipal resurfacing and private work, without the cost and site demands of a highway-size plant.

The four 80 t/h options

RMX-D80 RMX-B80 RMX-C80 RMX-M80
Type Drum mix (continuous) Stationary batch Containerized batch Mobile batch
Mixer — 1,000 kg/batch 1,500 kg/batch 1,000 kg/batch
Installed power 135 kW 285 kW 245 kW 241 kW
Foundation Light Concrete Compacted pad Compacted ground
Moves Rarely or trailer version Rarely Every 1–3 years Several times a year
Indicative FOB price $90,000 – $130,000 $190,000 – $240,000 $220,000 – $270,000 $240,000 – $300,000

Which one fits your work

What the site needs at 80 t/h

Item Rough daily need at 450 t of mix Notes
Aggregate about 425 t Separate bays per size; roof over sand and fines
Bitumen about 20–27 t At 4.5–6% binder; tank for several days’ supply
Fuel oil (batch plant) about 2.5–3.2 t From 5.5–7 kg/t in RMX-B/M parameters; more with wet aggregate
Power 135–285 kW installed Grid or generator with starting margin
Trucks typically 4–6 Depends on haul distance and paver speed
Water Dust suppression, cleaning Wet dust collectors need more

These are planning figures; your real numbers depend on mix design, moisture and haul distance.

Price and next steps

All four 80 t/h options are in our price guide. If your daily need is closer to 300 tons, a 60 t/h plant may do; above 700 tons, look at 120 t/h. Send us your project details for a recommendation.