Short answer: Tons per kilometer = width × thickness × 1,000 m × compacted density. At 2.35 t/m³, a 7 m wide road needs about 823 t per km for a 50 mm layer and about 1,645 t for 100 mm, and a single 3.5 m lane at 50 mm needs about 411 t. Use your mix design density and add a few percent for waste.

The tables below cover common widths and thicknesses, and the formula lets you work out any other case.

The formula

tons per km = width (m) × thickness (m) × 1,000 (m) × density (t/m³)

Example: 7 m × 0.05 m × 1,000 m × 2.35 t/m³ = 822.5 t per km.

Tons per kilometer at 2.35 t/m³

Width \ thickness 30 mm 40 mm 50 mm 60 mm 80 mm 100 mm
3.5 m (one lane) 247 t 329 t 411 t 494 t 658 t 823 t
5 m 353 t 470 t 588 t 705 t 940 t 1,175 t
6 m 423 t 564 t 705 t 846 t 1,128 t 1,410 t
7 m (two lanes) 494 t 658 t 823 t 987 t 1,316 t 1,645 t
7.5 m 529 t 705 t 881 t 1,058 t 1,410 t 1,763 t
10.5 m (three lanes) 740 t 987 t 1,234 t 1,481 t 1,974 t 2,468 t
14 m (four lanes) 987 t 1,316 t 1,645 t 1,974 t 2,632 t 3,290 t

For a different density, multiply by (your density ÷ 2.35).

Multi-layer pavements

Add the layers. A typical two-layer pavement on a 7 m road:

Layer Thickness Tons per km
Wearing course 50 mm 823 t
Binder course 60 mm 987 t
Total 110 mm 1,810 t

From tons to plant days and trucks

Step Example: 10 km, 7 m, 50 mm wearing course
Total tons 10 × 823 ≈ 8,230 t
Plant real daily output (120 t/h × 8 h × 75%) about 720 t
Production days about 11–12
Trucks (20 t, 60-min round trip) about 5–6

The capacity calculator does this for your own figures, and suggests a plant size.

Allowances to add

  • Waste and losses — start-up, cleaning, rejected loads
  • Irregular base — leveling courses on old pavements can add a lot
  • Tapers, junctions and shoulders — often missed in simple length × width figures
  • Density differences — use the mix design value, not a generic one

Common questions on site

Square meters per ton? At 50 mm and 2.35 t/m³, one ton covers about 8.5 m² (1 ÷ (0.05 × 2.35)).

Tons per square meter? At 50 mm: about 0.118 t/m²; at 40 mm: 0.094 t/m².

Loose vs compacted? These figures are compacted. A paver lays the mix loose and thicker; rollers bring it to the design thickness.

Need a plant sized to your road program? Send us the lengths, widths and layers, or compare plant sizes on the 120 t/h page.