Short answer: Tons per kilometer = width × thickness × 1,000 m × compacted density. At 2.35 t/m³, a 7 m wide road needs about 823 t per km for a 50 mm layer and about 1,645 t for 100 mm, and a single 3.5 m lane at 50 mm needs about 411 t. Use your mix design density and add a few percent for waste.
The tables below cover common widths and thicknesses, and the formula lets you work out any other case.
The formula
tons per km = width (m) × thickness (m) × 1,000 (m) × density (t/m³)
Example: 7 m × 0.05 m × 1,000 m × 2.35 t/m³ = 822.5 t per km.
Tons per kilometer at 2.35 t/m³
| Width \ thickness | 30 mm | 40 mm | 50 mm | 60 mm | 80 mm | 100 mm |
|---|---|---|---|---|---|---|
| 3.5 m (one lane) | 247 t | 329 t | 411 t | 494 t | 658 t | 823 t |
| 5 m | 353 t | 470 t | 588 t | 705 t | 940 t | 1,175 t |
| 6 m | 423 t | 564 t | 705 t | 846 t | 1,128 t | 1,410 t |
| 7 m (two lanes) | 494 t | 658 t | 823 t | 987 t | 1,316 t | 1,645 t |
| 7.5 m | 529 t | 705 t | 881 t | 1,058 t | 1,410 t | 1,763 t |
| 10.5 m (three lanes) | 740 t | 987 t | 1,234 t | 1,481 t | 1,974 t | 2,468 t |
| 14 m (four lanes) | 987 t | 1,316 t | 1,645 t | 1,974 t | 2,632 t | 3,290 t |
For a different density, multiply by (your density ÷ 2.35).
Multi-layer pavements
Add the layers. A typical two-layer pavement on a 7 m road:
| Layer | Thickness | Tons per km |
|---|---|---|
| Wearing course | 50 mm | 823 t |
| Binder course | 60 mm | 987 t |
| Total | 110 mm | 1,810 t |
From tons to plant days and trucks
| Step | Example: 10 km, 7 m, 50 mm wearing course |
|---|---|
| Total tons | 10 × 823 ≈ 8,230 t |
| Plant real daily output (120 t/h × 8 h × 75%) | about 720 t |
| Production days | about 11–12 |
| Trucks (20 t, 60-min round trip) | about 5–6 |
The capacity calculator does this for your own figures, and suggests a plant size.
Allowances to add
- Waste and losses — start-up, cleaning, rejected loads
- Irregular base — leveling courses on old pavements can add a lot
- Tapers, junctions and shoulders — often missed in simple length × width figures
- Density differences — use the mix design value, not a generic one
Common questions on site
Square meters per ton? At 50 mm and 2.35 t/m³, one ton covers about 8.5 m² (1 ÷ (0.05 × 2.35)).
Tons per square meter? At 50 mm: about 0.118 t/m²; at 40 mm: 0.094 t/m².
Loose vs compacted? These figures are compacted. A paver lays the mix loose and thicker; rollers bring it to the design thickness.
Need a plant sized to your road program? Send us the lengths, widths and layers, or compare plant sizes on the 120 t/h page.


