Short answer: With the new pad ready and an experienced crew, dismantling and re-installation each take days to about a week or two, plus travel time. Most of the work happens before the first bolt: pad, crane, trucks and permits ready. Empty and clean the system, label every cable and pipe, and recheck alignment, calibration and burner settings after the move.
Moving to the next project is the reason to own a containerized plant. Good planning means the plant never waits.
Step 1 — Plan the move (before shutdown)
| Task | Detail |
|---|---|
| Prepare the new site | Compacted, level, drained pad to the load drawing; stockpile area; access |
| Permits | Environmental and local permits for the new site — see permits |
| Transport | Trucks for each module; route survey for the heaviest and largest pieces; road permits |
| Crane | At both ends, sized for the heaviest lift |
| Crew | Same experienced crew for dismantling and re-installation |
| Utilities | Power or generator, fuel, water at the new site |
Step 2 — Shut down and clean
- Run out aggregate; burn out and cool the drum while turning
- Empty and clean the mixer, hot bins and silos
- Empty bitumen lines and the tank as far as practical; keep heating safe
- Purge the baghouse; clean bags
- Drain air and water lines
See the shutdown checklist.
Step 3 — Disconnect and label
- Lock out power and fuel
- Disconnect cables at plug connectors; label both ends
- Disconnect ducts, fuel, bitumen and air lines; cap open ends
- Secure loose parts inside modules for transport
Step 4 — Lift and transport
- Lift modules at the marked lifting points only
- Secure on trucks with suitable lashing
- Move in the order needed for re-installation at the new site
Step 5 — Re-install
| Order | Units |
|---|---|
| 1 | Cold feed and conveyors |
| 2 | Drying drum module |
| 3 | Mixing tower modules |
| 4 | Baghouse, ducts, stack |
| 5 | Filler silo, bitumen tanks, hot mix silo |
| 6 | Control room; reconnect cables by label |
| 7 | Fuel, bitumen and air lines |
Step 6 — Check and restart
- Level and align modules; check bolts
- Motor rotation and interlocks
- Recalibrate scales and feeders — see calibration
- Burner set-up for the new fuel and altitude — see burner tuning
- Trial mixes with the lab before full production
Make the next move easier
Keep a move file: lifting plan, module weights, cable labels, photos of connections, and notes on what slowed you down. Each move gets faster.