Short answer: Inspect at the factory before shipment: compare the plant component by component with the signed equipment list, check workmanship, run it empty in a dry run to test motors, burner, scales and controls, then check packing and documents. A defect found there costs days; on site it costs weeks. Write a report and agree open items before releasing the shipment.
Use this checklist yourself or give it to an independent inspector.
1. Compare with the equipment list
| Item | Check |
|---|---|
| Drying drum | Size, plate thickness, flights |
| Burner | Model, power, fuel |
| Baghouse | Area, bag material, fan |
| Mixer | Capacity per batch, paddles, liners |
| Scales | Load cell brand and capacity |
| Motors and gearboxes | Brands and power, as agreed |
| Silos, tanks, hot bins | Volumes and insulation |
| Control | PLC, screens, software language |
2. Workmanship
- Welds clean, no cracks or gaps.
- Paint complete, no rust through.
- Guards and handrails fitted.
- Cables labelled, cabinets tidy and sealed.
3. Dry run
- Start each motor, conveyor and fan in sequence.
- Light the burner.
- Test weighing with known weights.
- Test the control system, alarms and emergency stops.
- Note anything abnormal in writing.
4. Electrical
- Voltage and frequency match your site (see 50 Hz or 60 Hz).
- Earthing, cabinet ratings and cable sizes as specified.
5. Packing and documents
| Item | Check |
|---|---|
| Packing list | Matches the equipment list and marks |
| Oversize pieces | Identified, with lifting plan |
| Spare parts | Included as agreed |
| Manuals and drawings | Complete |
| Invoice and certificates | Consistent descriptions |
After the inspection
Write a short report with photos, list open items and agree who fixes them and by when. Only then release the shipment. See the shipping checklist and commissioning and training. Ask us about an inspection or video acceptance for your order.